China on track to hit 2020 target of 58GW nuclear power capacity

It's the fastest ramp up in history.

China’s installed capacity of 13GW for nuclear power in 2013 has increased to 20GW in 2014 and is well on track to hit its 2020 target of 58GW– with much of this front-end loaded.

According to a research note from Barclays, it estimates installed capacity increasing to 44GW by end-2017.

By 2020, China’s installed capacity would be at similar levels to France, just behind the US; and its 2030 ‘soft-target’ for installed nuclear capacity of 200GW would be double the current US capacity of 99GW.

China has taken 20 years to build 22 operating nuclear reactors, but 26 new units are expected to come on stream in the next 5 years.

Here's more from Barclays:

It has been 20 years since China commissioned its first nuclear power plant (NPP), but nuclear power in China is just starting to ramp up, and is on the verge of doubling installed capacity in the next 3 years. This would put it within reach of being the second largest nuclear plant operator in the world along with France and behind the US.

We examine the history, policy and regulatory background, equipment supply chain, project pipeline, and risks to the ramp up.

We also look at the implications of China’s nuclear ramp up for the power value chain – uranium miners (where we see the most positive impact), equipment suppliers, other power producers, and coal (which is most negatively impacted).

The ramp up of nuclear power in China is now close at hand, after over two decades since the first plant was built in 1993. Installed capacity of 13GW in 2013 has increased to 20GW in 2014 and is well on track to hit the 2020 target of 58GW– with much of this front-end loaded; we estimate an installed capacity of 44GW by end-2017.

By 2020, this would put installed capacity in China at similar levels to France, just behind the US; and China’s 2030 ‘soft-target’ for installed nuclear capacity of 200GW would be double US’s current capacity of 99GW.

China has taken 20 years to build 22 operating nuclear reactors, but 26 new units will come on stream in the next 5 years. This ramp up – the fastest in the history of the nuclear power generation industry – has profound implications across the power value chain. 

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Exclusives

India removes licence requirement to build transmission lines for bulk consumers
The rule applies to those with at least 25 MW of load for inter-state connection and at least 10 MW for intra-state.
NEFIN Group works double time to catch up on projects
CEO Glenn Lim explains how a delay turned out good as the company aims to reach 667 MW of capacity by 2026.
Summit Power International provides vital LNG support to Bangladesh
Without cross-border electricity supply, LNG is needed by a country facing geographical constraints to deploy renewables.