Japan's Chugoku submits decommissioning plan for Shimane NPP unit

Dismantling could take 30 years to complete.

According to World Nuclear News, Chugoku Electric Power Company has submitted an overview of its decommissioning plan for unit 1 of the Shimane nuclear power plant in Japan's Shimane prefecture to the country's nuclear regulator. The company expects dismantling of the plant to take 30 years to complete.

The utility submitted an outline of its plans for decommissioning the unit to the Nuclear Regulation Authority (NRA) on 28 April, having announced a year ago that it did not plan to restart the reactor.

During the first stage, all fuel is to be removed from the unit. This includes 722 used fuel assemblies that will be sent for reprocessing and 92 fresh fuel assemblies that will be stored in the unit's storage pool before being returned to the fuel fabricator.

Chugoku said it currently expects the decommissioning work to be completed by March 2046. However, it noted that while it has completed a detailed plan for the first phase of work, specific plans for the subsequent stages will be "based on the results of the status of radioactive contaminant that will be performed in Phase 1".

The company said it anticipates a total of some 60 tonnes of high-level waste to be generated during the decommissioning of Shimane 1, including components such as the control rods. A further 670 tonnes of intermediate-level waste, including the reactor vessel, will be produced, as well as 5350 tonnes of low-level waste. Some 20,680 tonnes of waste will not need to be treated as radioactive waste.

Shimane 1 was one of five older Japanese reactors to be officially declared for decommissioning in mid-March 2015 following the introduction of an accounting-related system earlier that month to determine which units should not be restarted. The other units included Kansai Electric Power Company's Mihama units 1 and 2, unit 1 of Japan Atomic Power Company's (JAPC's) Tsuruga plant, and Kyushu Electric Power Company's Genkai 1.

View the full report here

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Top News

ACEN bags $150m green loan
The fund will be used for its growth in other markets.
Lending & Credit
JERA establishes RE venture in London
This will support the company’s goal to attain 20 GW of renewables by 2035.
Project

Exclusives

Japanese utility firms into serious business of reselling LNG surplus
Declining local demand for LNG directs Japanese companies to the South and Southeast Asian markets.
Power Utility
India removes licence requirement to build transmission lines for bulk consumers
The rule applies to those with at least 25 MW of load for inter-state connection and at least 10 MW for intra-state.
NEFIN Group works double time to catch up on projects
CEO Glenn Lim explains how a delay turned out good as the company aims to reach 667 MW of capacity by 2026.
Summit Power International provides vital LNG support to Bangladesh
Without cross-border electricity supply, LNG is needed by a country facing geographical constraints to deploy renewables.