NHPC laments even pre-construction activities take a decade
NHPC`s recent hydro project monitoring report revealed that preconstruction activities take more than a decade tocomplete.
The report identified the usual culprits: the forest and environment clearances. Take the Teesta-IV for instance. After its ToR was approved by the environment ministry in 2009, stage-II forest clearance is expected to come through only by August, 2013. The likely date of getting environment clearance is September, 2012.
Yet, despite the nearly four year gap between ToR approval and forest clearance, it is more than probable that even this four year timeline will be overstepped.
The Indian government is already battling massive scams and such apathy to power projects.








ABB continues to strengthen the Symphony Plus platform with features and functionalities that meet the needs of a varied and changing power and water market.
The industry giant forays into the Mainland with the introduction of the turbocharged 6-cylinder 4006-23TRS gas engine.
Last December Alstom Grid announced it had acquired Canadian Smart Grid technology company ASAT Solutions - a strategic move to offer integrated substation data management solutions for utilities and industrial customers worldwide.
Modularity of hardware and software to meet the changing and individual requirements of modern grids during the whole life cycle
Following a trial phase with various grid operators, Siemens Smart Grid has brought the new protection device series Siprotec 5 onto the market.
















.jpg)




















