NHPC on track for timely commissioning of 132 MW Teesta HEP

NHPC is ensuring that erection of radial gate for bay-6 proceeds smoothly for a timely commissioning of its 132 MW Teesta Low Dam stage-III hydro electric project.

 

The rest of the HM works at the site are progressing as per schedule, with erection of radial gates already completed in bays 4, 5 and 7 and that for bay-3 progressing swiftly. However, the concreting works at barrage bays 1 and 2, out of a total of 7 bays, are yet to be completed.

With respect to power house works, NHPC has exceeded all targets set for the month of August. With a scheduled plan to achieve 250 cum and 300 cum of concreting in PH and TRC floor respectively, NHPC accomplished 336 cum and 365 cum of concreting during the month. In light of the progress made in all spheres, the first unit of the project is on track to be commissioned by May 2012.

The Teesta-III project envisages the construction of a 32.5 m high barrage across the Teesta river and a 125 m x 22 m x 56 m surface power house, with four Kaplan turbine generator units, of 33 MW capacity, each. The project would afford an annual energy generation of 594.07 million units (MU), assuming 90% performance.

Sign up for our newsletter

 

Do you know more about this story? Contact us anonymously through this link.

Click here to learn about advertising, content sponsorship, events & rountables, custom media solutions, whitepaper writing, sales leads or eDM opportunities with us.

Tags: dam commissioning

CO-WRITTEN ARTICLES & SPONSOR CONTENT ››

ABB continues to strengthen the Symphony Plus platform with features and functionalities that meet the needs of a varied and changing power and water market.
45 views

The industry giant forays into the Mainland with the introduction of the turbocharged 6-cylinder 4006-23TRS gas engine.
41 views

Last December Alstom Grid announced it had acquired Canadian Smart Grid technology company ASAT Solutions - a strategic move to offer integrated substation data management solutions for utilities and industrial customers worldwide.
61 views

Modularity of hardware and software to meet the changing and individual requirements of modern grids during the whole life cycle Following a trial phase with various grid operators, Siemens Smart Grid has brought the new protection device series Siprotec 5 onto the market.
46 views

LATEST POWER UTILITY JOBS »
  • No jobs posted on this category.
PRINT ISSUE »

Subscribe Now
Philippine major power grids nearing critical levels

2 views

China wind power sector stumbles but optimism prevails

1 view

Asian infrastructure face testing times

3 views

close Don't Show Again

STAY INFORMED! Get our free weekly newsletter