Taishan EPR reactor gets first concrete pour

Taishan EPR reactor gets first concrete pour

Around 9000 cubic meters of concrete were initially poured for the second Taishan EPR reactor in Guangdong, southern China.

The Chinese utility CGNPC needed seven pumps to continuously pour concrete in making the pre-reinforced Reactor Building slab, measuring 55 meters in diameter.

On November 26, 2007, AREVA and CGNPC signed a series of agreements worth an overall 10.7 billion to construct two third-generation EPR™ reactors, as well as supply all necessary equipment and services, and create an engineering joint-venture.

This contract is the largest international commercial contract signed in civil nuclear history.

The reactors are expected to be commissioned in late 2013 and 2014.

Do you know more about this story? Contact us anonymously through this link.

Click here to learn about advertising, content sponsorship, events & rountables, custom media solutions, whitepaper writing, sales leads or eDM opportunities with us.

MORE FROM AREVA
Areva to boost Aussie power station by 44MW
 Areva to boost Aussie power station by 44MW Areva will construct a $110.17 million solar thermal addition to CS Energy's coal-fired Kogan Creek power station.
Areva to work on 2 Indian nuclear projects
Bharat to start constructing nuclear forgings plant
Areva to work with Chinese nuclear firms
India nuclear plant with French reactors gets clearance
COMPANIES FEATURED
AREVA
TOP NEWS
India to increase funding for renewable energy by 130%
India to increase funding for renewable energy by 130% The rising cost of coal has been a godsend for India’s renewable energy industry.
Sumitomo yet to make investment decision for Indonesia
Bosch committed to solar plant investment in Malaysia
Indonesia to hike electricity prices
Power outages to slow down China’s economy
OTHER POWER UTILITY NEWS
Japanese-built power plant in Java switches on
Japanese-built power plant in Java switches on A new power plant completed ahead of schedule by the Japanese is now supplying Indonesia with 2,640 MW of badly needed electricity.
Sumitomo yet to make investment decision for Indonesia
Bosch committed to solar plant investment in Malaysia
Indonesia to hike electricity prices
Power outages to slow down China’s economy