MORE NEWSPublished: 06 Jul 11
414 views
Tata Power achieves full load generation for unit 1 of Maithon RBTPPTata Power completed coal firing in unit 1 of 1050 MW Maithon Right Bank Thermal Power Project in Dhanbad, state of Jharkhand.
The full load coal generation at unit 1 has also been achieved after the synchronization of the unit under standard requirements. The unit is scheduled to have commercial operation in first half of year 2012. Work on the balance of plants components is likely to be completed by first quarter of 2012. Tata Power has signed a connection agreement with Power Grid Corporation of India Limited and significant progress has been made for laying down power evacuation lines. In total, 96% work was completed by first half of this year for the power plant. Do you know more about this story? Contact us anonymously through this link. Click here to learn about advertising, content sponsorship, events & rountables, custom media solutions, whitepaper writing, sales leads or eDM opportunities with us. Tags: coal firing |