Policy reform first, financing last in ASEAN energy de-risking, report says
Reform, contracts and financial instruments will each cover risks the previous layer cannot.
De-risking ASEAN energy projects works only when applied in order, with policy reform, contracts, and financial instruments each covering the risks the previous layer cannot, according to the ASEAN Centre for Energy (ACE).
In its ASEAN Energy Investment 2026 report, ACE said the first layer is policy and regulatory reform, including integrated power-system planning, competitive procurement, regulatory certainty, and regional alignment for cross-border power trade.
The second layer is power purchase agreements (PPAs), which allocate the remaining risk between generator and offtaker, the report said.
Financial instruments such as guarantees, political risk insurance, currency hedging, and blended finance should cover only the residual risk, ACE said.
“A guarantee can cover payment default but cannot create missing transmission capacity,” the report said.
The report cited the Lao PDR–Thailand–Malaysia–Singapore Power Integration Project, ASEAN’s first multilateral cross-border electricity trading arrangement, which began full operations in October 2025.
Its second phase, launched in September 2024, doubled trading capacity to 200 megawatts and added Malaysia as a second exporter.
The ASEAN Power Grid Financing initiative offers up to $10b in Asian Development Bank financing over 10 years plus an initial $2.5b from the World Bank, ACE said.
The report set those facilities against an estimated $764b investment requirement for the grid by 2045.
Corporate PPAs are emerging in Vietnam, Malaysia, and Thailand, driven by demand from data centres and other electricity-intensive industries, according to the report.
Regional battery-storage investment exceeded $550m in 2025, but storage lacks a defined regulatory identity in most ASEAN member states, ACE said.
“Persistent reliance on first-loss support for mature technologies is itself diagnostic,” ACE said. “It indicates that underlying policy or offtaker risk remains unresolved and should be addressed through policy and utility reform rather than continued subsidy of the risk premium created by those gaps.”
It recommended that governments agree compatible minimum rules on wheeling, settlement, payment security, and dispute resolution before negotiating individual PPAs for grid interconnectors, citing the power integration project as precedent.
ACE also recommended that multilateral development banks apply concessional and first-loss capital with defined additionality and sunset clauses, reserving it for frontier markets, early-stage storage, geothermal exploration, and carbon capture.