, Taiwan

Ørsted pauses Taiwan offshore wind projects amidst permit woes

It failed to get an establishment permit for projects Changhua 1 and 2a in time.

Denmark-based firm Ørsted paused its projects in Taiwan and said it will revisit activities, timelines, and commitments after it failed to get an establishment permit in time to sign a 2018 power purchase agreement (PPA) with Taipower for the offshore wind projects, Changhua 1 and 2a, Offshore Wind reports.

The deadline for signing the 2018 PPA was extended to 2 January 2019. However, Taiwan’s Bureau of Energy had not issued an establishment permit by close of business local time.

According to the report, in November 2018 the Taiwanese government proposed a 2019 feed-in-tariff of TWD 5,106 per MWh ($165.6/MWh) and suggested a production cap of 3,600 annual full-load hours.

Ørsted Offshore CEO Martin Neubert commented, “We’re very concerned about the suggested feed-in-tariff level for 2019 as well as the newly proposed cap on annual full-load hours. We will need to see significant changes to these proposals before we can progress any further towards a final investment decision on the projects.”

“The proposed retrospective changes would jeopardise the creation of a local offshore wind supply chain, harm the planned transition to renewable energy and cause significant uncertainty among international investors looking to Taiwan,” the executive added.

The projects have a total capacity of 2.4GW and around 1.8GW has been earmarked for buildout in 2021 and 2025.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Exclusives

India removes licence requirement to build transmission lines for bulk consumers
The rule applies to those with at least 25 MW of load for inter-state connection and at least 10 MW for intra-state.
NEFIN Group works double time to catch up on projects
CEO Glenn Lim explains how a delay turned out good as the company aims to reach 667 MW of capacity by 2026.
Summit Power International provides vital LNG support to Bangladesh
Without cross-border electricity supply, LNG is needed by a country facing geographical constraints to deploy renewables.