Wastewater from the plants’ generators contained high levels of nitrate nitrogen that exceeded the allowable limit.

The Taichung City Government has fined the Taichung Power Plant $647,962 (NT$20 million) for poor management of industrial wastewater, Taipei Times reports.

It is the highest fine ever imposed on a state-owned enterprise, the report added.

The Taichung Environmental Protection Bureau has also given the coal-fired plant until 30 April to come up with a proposal to ameliorate the situation, bureau director-general Wu Chih-chao said in a statement posted on the city government’s website.

The plant, which is run by state-owned Taiwan Power Co (Taipower), was fined in accordance with Section 40 of the Water Pollution Control Act, Wu said. A test conducted on 21 March by the bureau found that wastewater from the plant’s No. 1 to No. 4 generators contained nitrate nitrogen levels that exceeded the allowable limit.

“Two other tests carried out earlier this year on generators No. 5 to No. 8 also turned up levels that exceeded the limit,” he Wu added.

The high nitrate nitrogen levels were mainly caused by the plant’s focus on preventing air pollution, resulting in a lack of capacity to manage water pollution, Taipower explained in a statement.

“We need to resolve the problem of wastewater first. We have yet to discuss whether to appeal the fine,” Taipower spokesman Hsu Tsao-hua said.

The plant has halved the output of generators No. 1 to No. 4, and readjusted an operating metre for flue gas desulfurization equipment to reduce the level of nitrogen oxides. Round-the-clock supervision of the generators is being enforced to regulate the quantity of ammonia injection, Taipower noted.

Generator No. 4 may also be shut down to test equipment and improve wastewater management, whilst adjustments would be made to generator No. 3 to improve air pollution controls.

Taipower said it hopes that improvements to the plant’s wastewater management could be made by early next month, as the nation’s electricity consumption is to greatly increase afterward, the report highlighted.

“It would maintain a low operating reserve margin of 6% over the next 10 days, as there have been no forecasts of abnormally hot weather,” Taipower said, adding that and adjustments would be made according to the weather and electricity consumption.

The company must pay the fine by 15 May, according to a separate report by the Chinese-language Liberty Times. 

Photo from Wikimedia Commons.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Exclusives

India removes licence requirement to build transmission lines for bulk consumers
The rule applies to those with at least 25 MW of load for inter-state connection and at least 10 MW for intra-state.
NEFIN Group works double time to catch up on projects
CEO Glenn Lim explains how a delay turned out good as the company aims to reach 667 MW of capacity by 2026.
Summit Power International provides vital LNG support to Bangladesh
Without cross-border electricity supply, LNG is needed by a country facing geographical constraints to deploy renewables.