Project

22 Feb 19
The PPAs with Copenhagen Infrastructure Partners and China Steel Corp will last for 20 years.
22 Feb 19
About 22% of investors are planning to increase their allocations to the sector by more than 20%.
20 Feb 19
South Korea’s proportion of renewable energy in power generation is set to increase to 20% by 2030.
20 Feb 19
 Foreign bidders involved in a consortium will be allowed to take up to 49% in the projects.
20 Feb 19
The minimum bid capacity has been set at 200 MW with individual project capacities of 50 MW minimum.
20 Feb 19
The survey is expected to end 15 March 2019.
15 Feb 19
Safety costs of the reactor were too high to bear.
15 Feb 19
It will accept bids from developers until 14 March 2019.
13 Feb 19
China Minsheng Investment Group has not returned money to bondholders that it had pledged to repay 1 February.
13 Feb 19
The plant is being built with India’s assistance.
13 Feb 19
It can now commission technical studies and analysis on the two projects.
13 Feb 19
Developers are flocking to Australia, India, and Japan, and other Asian countries.
12 Feb 19
It will be implemented at a fixed tariff of 2.8 cents per unit.
7 Feb 19
It needs more time for safety works.
6 Feb 19
It bought a 33.7MWp solar project in the Northern Territory of Australia.
6 Feb 19
The commissioning is currently expected for the end of 2019.
4 Feb 19
Companies are under pressure to sell or give up coal assets as Japan tries to meet its emissions targets.
4 Feb 19
The project cost is estimated to hit $1.83b.
30 Jan 19
SECI is becoming more lenient to developers.
30 Jan 19
Up to 180MW in capacity will be added to the grid.
30 Jan 19
The plant has 100MW capacity and uses 300,000 solar modules.
29 Jan 19
A leadership shake-up and tougher EU regulations could be dampening the utility’s spirits.
28 Jan 19
It will get a total investment of $126m.
28 Jan 19
The financing will support the efforts of both the private and public sector.
24 Jan 19
Leed Engineering, Voith Hydro, and Future Generation will be in charge of pre-construction, electrical, and mechanical and civil works.
23 Jan 19
The site of the firm’s project with TEPCO is a bottom-fixed area.
23 Jan 19
The project is located 100km south of its Changhua data centre.
18 Jan 19
Total investment for the 24 projects could hit $18.05b.
18 Jan 19
The winning bidder will be granted O&M work that will last for three years.
18 Jan 19
Projects include biomass gasification and micro-energy grids.
18 Jan 19
The two will collaborate on the $9.2b Choshi offshore wind project near Tokyo.
17 Jan 19
The projects will be spread across Lakshadweep’s 11 islands.
16 Jan 19
Huadian Group will take a 48% stake in the project.
16 Jan 19
Five utilities have lined up to buy the plant valued at around $188.47m.
16 Jan 19
It cited that it had sufficient capacity lined up for the coming years.
16 Jan 19
It raised the funds with UK-based Octopus Investments.
16 Jan 19
It reached financial close with MUFG Bank Malaysia.
11 Jan 19
It is already building the control centres for the 500MW and 400MW wind farms.
10 Jan 19
The plants, with a combined capacity of 6GW, aim to address energy wastage.