, India
Photo from Department of Atomic Energy

India’s Rajasthan Atomic Power Project unit-7 reaches criticality

This unit will now transition to the operational phase.

India's nuclear energy programme reached a major milestone after Unit-7 of NPCIL’s Rajasthan Atomic Power Project-7 & 8 (RAPP-7&8) achieved criticality. This development signifies the start of a controlled nuclear fission chain reaction in the 700-megawatt (MW) unit.

According to the Department of Atomic Energy, “reaching criticality in a nuclear reactor refers to the point at which a sustained and controlled nuclear fission chain reaction begins.”

“At this stage, the number of neutrons produced by fission events is equal to the number of neutrons lost through absorption and leakage, resulting in a stable level of power output,” it added.

Reaching criticality will allow the reactor to start generating heat that can be converted into electricity. 

Located in Rawatbhata, Rajasthan, RAPP-7 is a pressurised heavy water reactor, and the third unit in a series of sixteen indigenous reactors being developed in India.

Following this development, RAPP-7 will now transition from construction phase to its operational phase. 

A series of tests and experiments will be conducted to ensure the unit's optimal performance before it's connected to the grid. Power levels will be gradually increased, adhering to the Atomic Energy Regulatory Board's guidelines, until full power generation is achieved.

The RAPP-7&8 project, with a total planned capacity of 1,400 MW, adds to the existing six operational units at Rawatbhata, which contribute 1,180 MW to the grid. 

RAPP-7 is expected to commence power generation later this year, and the RAPP-8 the following year. 

NPCIL currently operates 24 reactors with a total capacity of 8,180 MW, with a capacity of 6,800 MW under construction. Ten other reactors, totalling 7,000 MW, are in the pre-project stage, projected to be completed by 2031-2032.

Jaringan listrik lemah Vietnam menghambat kebijakan pembelian listrik yang langsung

Infrastruktur energi yang buruk menghambat integrasi kapasitas baru dari proyek energi terbarukan (EBT).

Penutupan pembangkit listrik batu bara baru di ASEAN pada 2040 mungkin tercapai

Penambahan pembangkit batu bara baru dan retrofit pembangkit yang ada menjadi risiko lebih besar dalam transisi.

ADB menyetujui pinjaman senilai $500 juta untuk mendukung transisi energi Indonesia

Ini bertujuan membangun kerangka kebijakan yang kokoh dalam mendukung peralihan menuju energi bersih.

Avaada meningkatkan beban energi terbarukan untuk penuhi permintaan pusat data India

Perusahaan menargetkan kapasitas energi terbarukan sebesar 30 gigawatt pada 2030.

Asia-Pasifik mungkin tidak mencapai target energi terbarukan

Negara-negara di kawasan itu harus menarik investasi untuk memajukan tujuan energi bersih mereka.

Laba bersih Adaro turun 12% menjadi $880 juta di Semester 1

Pendapatan turun 15% menjadi $2,97 miliar pada periode tersebut.

ACEN dan Barito Renewables bermitra untuk mempercepat energi angin di Indonesia

Kemitraan ini akan dijalankan oleh anak perusahaan mereka.

Malaysia diminta mengintegrasikan jaringan listrik untuk mempercepat pertumbuhan tenaga surya

Pembatasan penetrasi tenaga surya ke jaringan pada 24% dari permintaan puncak dapat menghambat ekspansi.