Australia increases transfer capacity of Central-West Orana REZ to 7.7 GW

This was formalised under the Central-West Orana REZ access scheme.

The Energy Corporation of NSW (EnergyCo) has increased the amount of renewable generation and storage that can connect to the transmission network in the Central-West Orana Renewable Energy Zone (REZ) to 7.7 gigawatts (GW).

In a statement, EnergyCo said the increase in transfer capacity was formalised under the Central-West Orana REZ access scheme via a transfer capacity determination.  

The network capacity of 4.5 GW allows for 7.7 GW of renewable energy and storage projects to connect as wind, solar, and battery projects operate at different times of the day.

EnergyCo said the capacity increase does not expand the scope of the Central-West Orana REZ transmission corridor. Extensions are not currently proposed and would be subject to separate planning and regulatory approval processes.

Follow the link for more news on

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!