Gas turbine installation in UAE's Hamriyah Power Plant kicks off

Over 1,300 people have been mobilised for the project.

The first two of GE-supplied HA gas turbines for the 1.8 GW Hamriyah Independent Power Plant in the United Arab Emirates are currently undergoing installation and commissioning works, GE announced.

Once completed, the Hamriyah Independent Power Plant is anticipated to be the “most efficient power plant in the Middle East’s utilities sector,” GE added.

GE will supply three 9HA.01 units, other power generation equipment, as well as repair and maintenance services to the plant for 25 years.

GE has also provided the site with key equipment, such as two steam turbines, two gas turbine generators, two steam turbine generators, two Heat Recovery Steam Generators, two condensers, power island e-rooms, and step-up transformers.

More than 1,300 people have been mobilised for the project.

Codevelopers GE Energy Financial Services and Japan’s Sumitomo signed a 25-year power purchase agreement with Sharjah Electricity, Water and Gas Authority (SEWA) in 2018 to develop, build, and operate the plant.

The utilisation of the three 9HA.01 units would help SEWA cut carbon dioxide emissions by about four million tonnes per year as compared to present levels, which is equivalent to removing one million cars off of the UAE’s roads.

Currently, all civil works, nearly 85% of the procurement, and about 60% of construction and commissioning works are completed.
 

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Exclusives

India removes licence requirement to build transmission lines for bulk consumers
The rule applies to those with at least 25 MW of load for inter-state connection and at least 10 MW for intra-state.
NEFIN Group works double time to catch up on projects
CEO Glenn Lim explains how a delay turned out good as the company aims to reach 667 MW of capacity by 2026.
Summit Power International provides vital LNG support to Bangladesh
Without cross-border electricity supply, LNG is needed by a country facing geographical constraints to deploy renewables.