Shanghai Electric to supply 100 MW offshore wind farm

The winning bid involves supplying 26 wind turbines of 3.6 MW  each, according to a Bloomberg report.

Shanghai Electric Group Co., won a bid to supply turbines to a 100- megawatt offshore wind farm in the city, beating Sinovel Wind Group Co., China’s biggest producer of the equipment.

The winning bid involves supplying 26 wind turbines of 3.6 megawatts each at about 4,790 yuan ($749) a kilowatt, Zhang Bo, senior commercial manager of unit Shanghai Electric Windpower Equipment Co., said today in a phone interview. That’s 1.3 times the average turbine price for onshore wind projects in China in the second quarter, according to Bloomberg New Energy Finance.

Sinovel offered to supply 6-megawatt turbines at 5,298 yuan a kilowatt for the second phase of the East China Sea Bridge wind farm, while XEMC Windpower Co., a unit of Xiangtan Electric Manufacturing Co., bid 8,000 yuan a kilowatt, Zhang said.

China’s goal of installing 30 gigawatts of offshore wind energy by 2020 has prompted turbine makers to develop larger machines. Building work on the project by a unit of China Datang Corp., the nation’s second-biggest power producer, is expected to begin by the end of the year, Zhang said. Datang’s unit also built the 102-megawatt offshore wind project near the East China Sea Bridge in Shanghai, with 3-megawatt turbines from Sinovel.

 

Photo from Ruud Schreuder

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Exclusives

Will the government pay for coal power exit in Vietnam?
The country’s coal power phase-out strategy sees renewables accounting for 67.7%–71.5% of the energy mix by 2050.
IPP
India removes licence requirement to build transmission lines for bulk consumers
The rule applies to those with at least 25 MW of load for inter-state connection and at least 10 MW for intra-state.
NEFIN Group works double time to catch up on projects
CEO Glenn Lim explains how a delay turned out good as the company aims to reach 667 MW of capacity by 2026.