Power plant: VN gets bogged down in mud created by Chinese contractor

The investors of the Nong Son thermopower plant project might feel regret for their decision to let a Chinese company execute the project. Kicked off in 2008, but the project has not been completed.

 

Offering the low bidding prices, the Chinese contractor won the bid to undertake the Nong Son thermopower plant project in Quang Nam province.

The agriculture land fund has been narrowed, the agriculture production has decreased, the transport system has been broken off – all these are the things the Chinese contractor has created on the construction site so far.

Half-done power project kills agriculture production

When starting the project execution, CMCH – the Chinese contractor - promised that the construction work would be completed soon so that the plant would become operational in 2010.

However, in fact, the execution had been going very slowly until it completely stopped operation some months ago.

Nguyen Van Nam, a farmer, who has been cultivating on the field next to the coal mining site, complained that the waste water leaking from the coal mine has caused serious pollution to the environment, thus making rice and farm produce unable to grow.

Nguyen Kim Dung, Chair of the Que Trung Commune People’s Committee, has affirmed that Nong Son hamlet has most suffered from the coal mine and the construction plant. Previously, there were 30 hectares of land in the hamlet, while 50 percent of the land has been filled up by the coal.

The environment pollution caused by the coal exploitation has led to bad crops and low productivity. In the past, local residents could harvest six tons of rice and farm produce a crop, while they now can get 3.5-3.7 tons.

As a result, people have given up farming. They dare not pour money into the cultivation because they fear they would waste the money if the land gets worse and cannot bring the productivity high enough.

The bidding prices offered by Chinese contractors are really low?

T, a security guard of the power plant, told reporters that Chinese workers on the construction site left for home some months ago, while only four of them have been staying in Vietnam.

“Materials and equipment have all broken down. There’s nothing valuable here for us to protect,” T said.

The construction site, which was very noisy one year ago, has turned quiet. The road to the factory has been used as the place to dry rice.

“Though equipment and materials have broken down, the Chinese contractor still asks us to keep tight security. We will be heavily punished if we neglect our duty. I don’t know what the four Chinese workers are doing here,” he said.

According to Vo Dinh Dat, Deputy Director of the Nong Son Coal and Power Company, a subsidiary of the Vietnam Coal and Mineral Industries Group (Vinacoal) – the investor of the project, only 55 percent of the project’s works have been fulfilled.

“At first, they (the Chinese contractor) brought 400 workers, but later the workers left one after another,” Dat said.

“The contractor simply informed that they were meeting some unfavorable conditions, including the regular floods and financial difficulties,” he added.

Sources have said that the two sides have sit to discuss the solution to the problem, while the Chinese contractor has promised to bring workers back to the site.

Especially, the contractor now intends to increase the bidding prices. And if so, the bidding prices offered by Chinese contractors are not always low as Vietnamese investors think.

 


https://english.vietnamnet.vn/fms/business/51265/power-plant--vn-gets-bogged-down-in-mud-created-by-chinese-contractor.html


 

Jaringan listrik lemah Vietnam menghambat kebijakan pembelian listrik yang langsung

Infrastruktur energi yang buruk menghambat integrasi kapasitas baru dari proyek energi terbarukan (EBT).

Penutupan pembangkit listrik batu bara baru di ASEAN pada 2040 mungkin tercapai

Penambahan pembangkit batu bara baru dan retrofit pembangkit yang ada menjadi risiko lebih besar dalam transisi.

ADB menyetujui pinjaman senilai $500 juta untuk mendukung transisi energi Indonesia

Ini bertujuan membangun kerangka kebijakan yang kokoh dalam mendukung peralihan menuju energi bersih.

Avaada meningkatkan beban energi terbarukan untuk penuhi permintaan pusat data India

Perusahaan menargetkan kapasitas energi terbarukan sebesar 30 gigawatt pada 2030.

Asia-Pasifik mungkin tidak mencapai target energi terbarukan

Negara-negara di kawasan itu harus menarik investasi untuk memajukan tujuan energi bersih mereka.

Laba bersih Adaro turun 12% menjadi $880 juta di Semester 1

Pendapatan turun 15% menjadi $2,97 miliar pada periode tersebut.

ACEN dan Barito Renewables bermitra untuk mempercepat energi angin di Indonesia

Kemitraan ini akan dijalankan oleh anak perusahaan mereka.

Malaysia diminta mengintegrasikan jaringan listrik untuk mempercepat pertumbuhan tenaga surya

Pembatasan penetrasi tenaga surya ke jaringan pada 24% dari permintaan puncak dapat menghambat ekspansi.