Thailand's MEA power line to be delayed another year

Here's what to blame.

According to Maybank Kim Eng, the Metropolitan Electricity Authority's (MEA) underground electricity transmission line worth THB5.69b is expected to be delayed another year, says acting governor Somchai Roadrungwasinkul.

Here's more:

The project with a total length of 49.6 kilometres in the Sukhumvit, Phahon Yothin, Phayathai, Pathumwan, Chong Nonsi and Rama III districts that started in 2008 was projected to be completed last year.

The MEA was also assigned by the government to lay an underground transmission line along Ratchadaphisek Road from the Asoke to the Rama IX intersection, next to the subway line in a project worth THB8.89b.

The utility also conducted a feasibility study to expand 129.4 km of underground power transmission lines in inner Bangkok and business districts, which would cost THB140b.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!