The website caries here, an account of 47 thermal power plants (TPPs) that have exhibited more than 100 million units (MU) worth of

shortfall vis-a-vis their targets during April - July, 2011.Various issues, such as low system demand, miscellaneous forced shortages,

etc. have contributed to a cumulative shortfall of 11,970.8 million units (MU) in targeted power generation for 47 stations, worth

combined capacity of 37,359.25 MW.
 
NTPC Limited was faced with low system demand at its 830 MW Dadri combined cycle power plant (CCPP), and 663 MW Auraiya

CCPP; while the 2340 MW Kahalgaon TPS suffered from fuel shortages, reflected in maximum generation losses worth 1068 MU.

Further, Talcher STPS, Udupi TPP, Peguthan CCPP and Jalipa Kupurdi TPS  recorded shortfalls of 567.94 MU, 465.95 MU,

450.86 MU and 390.03 MU respectively, among others.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!