Tata Power concludes hydro tests for Mundra UMPP

Tata Powerhas completed milestones for units 1, 2 and 3 associated with its 4000 MW Mundra Ultra Mega Power Project.

Amongst the five units of 800 MW each, units 2 and 3 witnessed maximum progress in first half of year 2011. The boiler hydro test for unit 3 was successfully completed in March and main steam line hydro test was recently finished in May. With the current status of the ongoing activities, the boiler light is expected to be up in August.

Furthermore, at unit 1, the steam blowing process that commenced in March was concluded within 3 months. The synchronization is expected to take place in July whereas commercial operations is scheduled to be achieved by September. In the remaining units, engineering, procurement and construction activities are progressing sequentially as per schedule. All four units, except unit 1, are targeted for completion in year 2013. Overall, approximately 83% of the work is complete for Mundra UMPP.
 

Follow the link for more news on

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you design and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Top News

India issues 1,870 MW renewable energy tenders in November
Major investments fuel hybrid projects and battery storage, stabilising India's grid.
Sri Lanka secures $100m loan for power sector reform
Unbundling the CEB boosts financial sustainability and opens the door for renewables.
Solar profitability rises 9% in Southeast Asia with battery integration
Stable policies and foreign investment are vital to unlock the region's solar potential.
ADB approves $650m loan to accelerate India's solar deployment
Policy reforms and loans will remove financial barriers to solar installation.