All 1,500 towers built for Australia’s 700km EnergyConnect backbone

The project is 90% complete and scheduled for finishing in 2026.

All 1,500 steel towers of the 700-kilometre (km) backbone of EnergyConnect project have been constructed.

According to Transgrid, the final tower was erected at Bundure in the Riverina region, marking a significant milestone for the nation-critical project which will increase renewable energy sharing between New South Wales, South Australia and Victoria.

Line stringing works have also been completed, with 10,385 km of high-voltage conductor cabling installed, enough to span from Sydney to Perth three times.

The 159 km western section of EnergyConnect, from Buronga, NSW to the South Australia border and Red Cliffs in Victoria, has already been completed and energised, including construction of one of the biggest and most complex substations in the Southern Hemisphere.  

Construction of the world-class Dinawan substation at Bundure is being finalised, and a major expansion of Wagga Wagga substation has also been completed.  

“We have achieved extraordinary progress in construction of the project this year, which is now 90% complete and on schedule to be finished in 2026,” said Executive General Manager of Major Projects Gordon Taylor.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you design and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!