Oz must generate 33TWh of new renewable generation capacity by then.

According to the Renewable Energy Target 2016 Administrative Report released by the Clean Energy Regulator, Australia is on track to meet its 2020 renewable generation target. 

Enerdata said that the report highlights progress toward the Renewable Energy Target (RET), which requires Australia to generate 33 TWh of new renewable generation capacity by 2020, resulting in covering more than 23% of power generation with renewables by 2020.

In 2016, renewable power plants generated 18.3 TWh. One-third of the new build required to meet the target of 33 TWh was either fully financed or supported by a power purchase agreement in 2016.

Here's more from Enerdata:

Once built, this will increase large-scale generation to more than 23 TWh in 2018. During the year, 98 large-scale renewable power plants were accredited, corresponding to a total capacity of 494 MW (including five wind parks totalling 365 MW, 10 large solar plants above 1 MW totalling 102 MW and 76 solar projects below 1 MW totalling 16 MW).

The total capacity of committed projects in 2016 reached 1.35 GW (869 MW of wind and 481 MW of solar), which should generate more than 3.9 TWh/year.

This story was originally published by Enerdata.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Exclusives

Japanese utility firms into serious business of reselling LNG surplus
Declining local demand for LNG directs Japanese companies to the South and Southeast Asian markets.
Power Utility
India removes licence requirement to build transmission lines for bulk consumers
The rule applies to those with at least 25 MW of load for inter-state connection and at least 10 MW for intra-state.
NEFIN Group works double time to catch up on projects
CEO Glenn Lim explains how a delay turned out good as the company aims to reach 667 MW of capacity by 2026.
Summit Power International provides vital LNG support to Bangladesh
Without cross-border electricity supply, LNG is needed by a country facing geographical constraints to deploy renewables.