, India

Conflicts settled for Bihar mega power project

The foundation stone of the Nabinagar Super Thermal Power Project in Aurangabad district has been laid.

 

This marks the end of tussles over land acquisition and rehabilitation, officials said.

After laying the foundation stone of the first stage of the 3x660 MW project at Shivanpur village near Nabinagar,Bihar Chief Minister Nitish Kumar also announced a fresh compensation package for the farmers whose land is being acquired for the plant.

Demanding increased compensation, hundreds of farmers have been protesting against the project for nearly a year and stopped work at the site.

Soon after the ground breaking ceremony on Jan 14, 2011, local farmers had protested over construction work at the site.

Over 2,800 acres of mostly single-crop agricultural land has been acquired in eight villages each of Nabinagar and Barun block in Aurangabad.

The project is a 50:50 joint venture of Bihar State Electricity Board and National Thermal Power Corporation.

"This mega power project has special importance for Bihar as it will provide light to thousands of houses in villages," he said.

BSEB officials said the first unit of the project is targeted to be commissioned in 2015 and the other two units at intervals of six months each thereafter. The state will get 70 percent of the power generated by it, while the balance will go to other states of the eastern region.

For the source of this story, click here.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Exclusives

India removes licence requirement to build transmission lines for bulk consumers
The rule applies to those with at least 25 MW of load for inter-state connection and at least 10 MW for intra-state.
NEFIN Group works double time to catch up on projects
CEO Glenn Lim explains how a delay turned out good as the company aims to reach 667 MW of capacity by 2026.
Summit Power International provides vital LNG support to Bangladesh
Without cross-border electricity supply, LNG is needed by a country facing geographical constraints to deploy renewables.