GREL on track for Vermagiri CCPP commissioning

 

GMR Rajahmundry Energy Limited is on track to meet the commissioning deadline for the 768 MW combined cycled power plant. A GMR Energy-subsidiary, GREL has already wrapped up around 68.8 per cent of the overall project in Vermagiri, with 80 per cent of equipment procured and one-third of the construction done.


 While the structural works for the switchyard and erection of the battery bank and charger have been completed, the erection of cable tray and unit auxiliary transformers is presently underway.


Foundation excavation for gas conditioning system has also commenced at the project site.


Besides, both the generator and gas turbine sets, have reached the site and other equipments like the Heat Recovery Steam Generator modules, switchyard, electrical equipments etc. have also started reaching the venue.

Equipment like boiler pumps, cooling water pumps, condenser tubes, transformer relay protection have also reached the site.
 

Follow the link for more news on

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!