Japan OKs draft safety report for Tomari-3

The review took nearly 12 years to complete.

Japan's Nuclear Regulation Authority (NRA) has approved the draft safety assessment report for Tomari-3 (PWR, 912 MWe), with formal approval expected this summer.

According to Japan Atomic Industrial Forum (JAIF), the process took nearly 12 years, the longest for any nuclear reactor under post-Fukushima safety standards. The delay was attributed to the “extensive evaluations required to confirm the absence of active faults at the site.”

Safety upgrades are generally complete, except for a 19-metre seawall designed for tsunami protection, which is still under construction.

Further steps—including approval of operational safety programs and securing consent from local governments—remain necessary, particularly from the municipalities of Tomari Village, Kyowa Town, Iwanai Town, Kamoenai Village, and from Hokkaido Prefecture.

Following this development, the total number of Japanese reactors passing the new standards has reached 18. 

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you design and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Top News

Utility scale battery storage costs fall to US$125 per kWh
Core equipment costs can rise to around US$100 per kilowatt-hour or more in markets with higher tariffs, among others.
Power sector shift drives coal consumption down after record 2025
Coal usage will decline due to increasing competition with other energy sources.
NTPC boosts solar capacity at Khavda projects in Gujarat
The solar energy expansion strengthens India’s renewable footprint nationwide.
Power Utility
India boosts bioenergy with ₹998 crore MNRE funding
Bioenergy capacity supported through government financial assistance.
Project