Subansiri hydroelectric project way behind schedule, says CEA

 

The CEA calls NHPC’s aim to commission the first unit of its 2000 MW Subansiri Lower hydroelectric plants by December 2013 as too ambitious.


A tour report on the project revealed that a plethora of critical milestones still remains to be achieved, according to India’s Central Electricity Authority director Manoj Sikdar.


There is a large volume of civil works that is yet to be completed and their present rate of progress of excavation of tunnels, erection of steel liners in vertical pressure shaft and other such activities is too slow to meet the deadline.


The report also noted that the contract for the cut off wall at the dam site is yet to be signed with the finalized party.



The CEA feels that the National Hydroelectric Power Corporation’s project authorities are way behind the project commissioning schedule.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Exclusives

Will the government pay for coal power exit in Vietnam?
The country’s coal power phase-out strategy sees renewables accounting for 67.7%–71.5% of the energy mix by 2050.
IPP
India removes licence requirement to build transmission lines for bulk consumers
The rule applies to those with at least 25 MW of load for inter-state connection and at least 10 MW for intra-state.
NEFIN Group works double time to catch up on projects
CEO Glenn Lim explains how a delay turned out good as the company aims to reach 667 MW of capacity by 2026.