Mundra ultra mega power project almost completed

 Seventy-seven per cent of the work at Tata Power's 4,000 MW Mundra ultra mega power project has been completed.

 

The the steam blowing of Unit-1 currently in progress. The unit is scheduled to be synchronized in July this year, and is expected to start commercial operations by the end of the second quarter.

Boiler light up of Unit-2 of the UMPP is programmed for completion in August 2011, and along with units 3, 4 and 5, it is expected to be commissioned in 2012-13, the first year of the 12th Plan.

Meanwhile, the 400 kV transmission lines covering Mundra-Vadavi, Mundra-Jetpur, Mundra-Limbdi, and Gandhar-Navsari, designed to evacuate power from the massive plant are also under development.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!