, Vietnam

Vietnam's wind power capital not attracting investors

Considered Vietnam's wind power capital.

Yet the central province of Bin Thuan, with as many as 20 wind power projects planned for development until 2020, is not likely to meet capacity targets.

It turned out that investors are discouraged by the long time to recoup their investments.

Under the development master plan for the 2011 – 2020 period, the wind farms in Binh Thuan are expected to reach the installed capacity of 700MW, with nearly 1,500 kWh of total equivalent wind power output.

“But the target seems unfeasible,” said Duong Tan Phong, head of power and energy management of the provincial Department of Industry and Trade.

He added that the best that can be done is to lower it to 500MW.

The largest obstacle at the moment is the lack of capital from the investors, he analyzed.

“A turbine for wind power costs millions of US dollars, but it takes quite a long time to recoup investments.

In 2010 the PV Power RE Co Ltd broke ground on the Phu Quy wind power project with three turbines.

The VND335-billion project with a total capacity of 6MW officially became operational last August with the first two turbines beginning supplying power for the area. 

But the company will have to earmark some VND10 billion on an annual basis in order to offset losses from the project, company director Pham Cuong said.

For more.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Exclusives

India removes licence requirement to build transmission lines for bulk consumers
The rule applies to those with at least 25 MW of load for inter-state connection and at least 10 MW for intra-state.
NEFIN Group works double time to catch up on projects
CEO Glenn Lim explains how a delay turned out good as the company aims to reach 667 MW of capacity by 2026.
Summit Power International provides vital LNG support to Bangladesh
Without cross-border electricity supply, LNG is needed by a country facing geographical constraints to deploy renewables.