India set to miss power capacity addition target


India scaled down its set target of additional power generation capacity from 20,359MW to 18,600MW for 2010.




This is due to shortage of power generation equipment, delayed investment decisions, contractual problems, resistance to land acquisition, delays in environmental and forest clearances, geological issues and natural calamities. This will aggravate the current 12% peak-hour power shortage.


The country has commissioned a capacity of 7,059MW so far in the current fiscal. In 2009-10, India added a capacity of 9,585MW as against a target of 14,500MW.


“Apart from the usual problems like delays in equipment supplies, we also had the misfortune of natural calamities as in the case of floods that damaged the commissioning of the first unit of Tehri Hydro Development Corp. Ltd’s 400MW Koteshwar power project,” said a top power ministry official, who did not want to be named.

Follow the link for more news on

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Exclusives

Will the government pay for coal power exit in Vietnam?
The country’s coal power phase-out strategy sees renewables accounting for 67.7%–71.5% of the energy mix by 2050.
IPP
India removes licence requirement to build transmission lines for bulk consumers
The rule applies to those with at least 25 MW of load for inter-state connection and at least 10 MW for intra-state.
NEFIN Group works double time to catch up on projects
CEO Glenn Lim explains how a delay turned out good as the company aims to reach 667 MW of capacity by 2026.