Coal-fired Eraring Power Station retirement postponed to 2027

Started in 1984, the plant is initially targeted for closure as early as August 2025.

Origin and the New South Wales Government have agreed to delay the closure of the 2,880-megawatt (MW) Eraring Power Station by two years to 19 August 2027 to support the state’s power supply amidst the energy transitions.

In a statement, Origin said that under the Generator Engagement Project Agreement (GEPA), the government will help cover the cost of the plant’s operations during the extension periods where it will generate six terawatt-hours of power annually

“We believe this agreement strikes the right balance, with an extension to operations enabling Eraring to continue supporting the security of electricity supply in New South Wales through the energy transition, while making compensation available to Origin in the event economic conditions for the plant are challenging,” Origin CEO Frank Calabria said.

ALSO READ: Origin Energy expands RE portfolio with Yanco Delta Wind Farm acquisition

“This agreement supports Eraring to continue to play an important role in maintaining reliable power for businesses and households through a period in which there remains considerable uncertainty about the volume and timing of new renewables, transmission and firming infrastructure coming online,” he added.

The GEPA also indicated that Origin may recover a portion of the Eraring losses for an upcoming financial year using an agreed formula, capped at $149.4m (A$225m) per year.

If the operations are profitable, Origin will pay the government 20% of the profit with a maximum amount of $26.6m (A$40m) per annum.

The agreement also stated that the Origin still has the right to determine the final retirement timeline of the four Eraring units but there will be no state compensation after 2027 and all units must shut down no later than April 2029.

$1 = A$1.51

Follow the link for more news on

Jaringan listrik lemah Vietnam menghambat kebijakan pembelian listrik yang langsung

Infrastruktur energi yang buruk menghambat integrasi kapasitas baru dari proyek energi terbarukan (EBT).

Penutupan pembangkit listrik batu bara baru di ASEAN pada 2040 mungkin tercapai

Penambahan pembangkit batu bara baru dan retrofit pembangkit yang ada menjadi risiko lebih besar dalam transisi.

ADB menyetujui pinjaman senilai $500 juta untuk mendukung transisi energi Indonesia

Ini bertujuan membangun kerangka kebijakan yang kokoh dalam mendukung peralihan menuju energi bersih.

Avaada meningkatkan beban energi terbarukan untuk penuhi permintaan pusat data India

Perusahaan menargetkan kapasitas energi terbarukan sebesar 30 gigawatt pada 2030.

Asia-Pasifik mungkin tidak mencapai target energi terbarukan

Negara-negara di kawasan itu harus menarik investasi untuk memajukan tujuan energi bersih mereka.

Laba bersih Adaro turun 12% menjadi $880 juta di Semester 1

Pendapatan turun 15% menjadi $2,97 miliar pada periode tersebut.

ACEN dan Barito Renewables bermitra untuk mempercepat energi angin di Indonesia

Kemitraan ini akan dijalankan oleh anak perusahaan mereka.

Malaysia diminta mengintegrasikan jaringan listrik untuk mempercepat pertumbuhan tenaga surya

Pembatasan penetrasi tenaga surya ke jaringan pada 24% dari permintaan puncak dapat menghambat ekspansi.