Genesis Energy restarts Huntly Unit 5

The 400 MW unit experienced an outage on 30 June.

New Zealand-based Genesis Energy has restarted the operations of the 400-megawatt (MW) Unit 5 combined cycle gas turbine at the Huntly Power Station.

The unit, which can power up to 400,000 households, experienced an unexpected outage on 30 June due to the failure of its main circuit breaker, with specialist parts needing to be procured overseas.

The unit came back online on 20 January, four months earlier than expected, Genesis said.

ALSO READ: FRV Australia reaches financial close for 63 MW solar farm

“It’s pleasing to see the unit once again contributing to New Zealand’s electricity supply, particularly as we look ahead to winter. Unit 5 and Huntly Power Station as a whole provide essential back-up to weather-dependent generation from water, wind and sun, and in times of unplanned plant outages and natural disasters,” said Chief Wholesale Officer Tracey Hickman.

“We look forward to working with others in the sector to ensure the insurance Huntly is able to provide is available longer term,” Hickman added.

Genesis used all three Rankine units to compensate for Unit 5’s outage.

 

Follow the link for more news on

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Exclusives

India removes licence requirement to build transmission lines for bulk consumers
The rule applies to those with at least 25 MW of load for inter-state connection and at least 10 MW for intra-state.
NEFIN Group works double time to catch up on projects
CEO Glenn Lim explains how a delay turned out good as the company aims to reach 667 MW of capacity by 2026.
Summit Power International provides vital LNG support to Bangladesh
Without cross-border electricity supply, LNG is needed by a country facing geographical constraints to deploy renewables.