PT Pertamina starts full operation for Lumut Balai Unit 2 geothermal plant

This added 55 MW to the company’s total installed capacity.

PT Pertamina Geothermal Energy Tbk (PGE) has announced that its Lumut Balai Unit 2 Geothermal Power Plant has reached full operational capacity and has started supplying power to the national grid.

In a statement, the company said this development added 55 megawatts (MW), bringing its total installed capacity to 727.5 MW across six operational areas, just

PGE said this follows a 72-hour continuous Unit Rated Capacity (URC) test and the issuance of the Commissioning Certificate on 29 June.

“With this additional capacity, we are not only strengthening the national energy mix but also moving closer to our goal of reaching 1 gigawatt (GW) of independently-managed installed capacity within the next 2-3 years,” PGE President Director Julfi Hadi said.

Hadi said the company will continue supporting the national geothermal capacity expansion target of 5.2 GW during that period.

PGE is also developing several other strategic projects, including the Hululais Geothermal Power Plant Units 1 & 2 (110 MW), as well as a number of co-generation projects with a combined capacity of 230 MW.

The company has also inaugurated the exploration phase (green field) of the Gunung Tiga geothermal power plant in Lampung, which holds a potential capacity of 55 MW.

Follow the link for more news on

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you design and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Top News

Global geothermal investment is set to grow20% a year to 2030
On a dollars-per-watt basis, Rystad estimates district heating costs at roughly US$3 per watt.
India issues 1,870 MW renewable energy tenders in November
Major investments fuel hybrid projects and battery storage, stabilising India's grid.
Sri Lanka secures $100m loan for power sector reform
Unbundling the CEB boosts financial sustainability and opens the door for renewables.
Solar profitability rises 9% in Southeast Asia with battery integration
Stable policies and foreign investment are vital to unlock the region's solar potential.