, India

NTPC installed capacity increases to 32694 MW

The first 500 MW unit of Indira Gandhi Super Thermal Power Project at Jhajjar has been commissioned after achieving full load.

The unit has achieved full load on October 31st 2010, which is 39 months and 25 days from the date of investment approval, a new record for Greenfield projects.

The 1500 MW Project is being set up by Aravali Power Company Private Limited a joint venture of NTPC Limited, Govt. of Haryana and Govt. of Delhi. The power from this project will be supplied to Haryana and Delhi on 50:50 basis.

The total installed capacity of NTPC has now risen to 32694 MW. Currently,16840 MW capacity is under construction, about 7000 MW is under bidding and Feasibility Reports have been finalized for another 13000 MW .Thus, NTPC is on course to become a 75000 MW company by 2017.



 

Follow the link for more news on

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Exclusives

India removes licence requirement to build transmission lines for bulk consumers
The rule applies to those with at least 25 MW of load for inter-state connection and at least 10 MW for intra-state.
NEFIN Group works double time to catch up on projects
CEO Glenn Lim explains how a delay turned out good as the company aims to reach 667 MW of capacity by 2026.
Summit Power International provides vital LNG support to Bangladesh
Without cross-border electricity supply, LNG is needed by a country facing geographical constraints to deploy renewables.