Samsung to build Malaysian gas turbine power plant

A RM2.47 billion EPC contract.

This has been awarded by Tenaga Nasional Bhd to Samsung to develop a 1,000 to 1,400MW combined cycle gas turbine power plant in Prai, Penang.

Samsung will be responsible for the plant design and engineering, supply of power island equipment with its related auxiliaries and ancillaries and construction of all plant infrastructure under the development.

The RM2.47 billion project cost includes the EPC works of RM1.88 billion and development costs.

Expected to take 32 months to complete, the project will potentially increase the net assets of the group by about 0.56%.

For more.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!