China grants priority access to new grid capacity to renewable energy firms

This is in line with its goal to ease burden on these firms.

The Chinese National Energy Administration (NEA) has ordered local authorities to relieve renewable power generation companies by strengthening guaranteed purchase agreements and offering them priority access to new grid capacity.

As per the current renewable energy regulations, power transmission companies (TSOs) have to take all the power generated by renewable energy sources (such as wind and solar power) but many projects do not have proper grid access ("curtailment" issue). The NEA plans to ensure a stricter implementation of the law and will slow the pace of projects under construction failing to secure guaranteed PPAs.

According to the NEA, China lost nearly 42 TWh of wind power in 2017 (12%) of total wind generation and 7.3 TWh (6% of total solar generation) due to curtailment. In the first quarter of 2018, wind curtailment rate fell to 8.5% and solar curtailment rate to 4.3%.

This article was originally published by Enerdata.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Exclusives

India removes licence requirement to build transmission lines for bulk consumers
The rule applies to those with at least 25 MW of load for inter-state connection and at least 10 MW for intra-state.
NEFIN Group works double time to catch up on projects
CEO Glenn Lim explains how a delay turned out good as the company aims to reach 667 MW of capacity by 2026.
Summit Power International provides vital LNG support to Bangladesh
Without cross-border electricity supply, LNG is needed by a country facing geographical constraints to deploy renewables.