Staff Reporter
Blackout-plagued Mindanao to shutdown 3 power plants
Blackout-plagued Mindanao to shutdown 3 power plants
Mindanao will shut down three Agus-Pulangi power plants for a month beginning on April 17 to undergo repairs and rehabilitation.
Power sector overcomes technological limitations, benefits from addition of 6,080 MW of super critical units in 11th plan
Efforts to overcome hindrances in the power sector are finally paying off, with the nation having managed to achieve great heights in the areas of capacity addition, electricity generation and technology. 8Although the government authorities have repeatedly faced flak for the sector's supposedly dismal performance over the past five years, the Central Electricity Authority's (CEA) recent report highlighting power sector accomplishments proves otherwise. 8The nation has benefitted immensely from the technological advancement during the previous plan period. Nine super critical technology units, totaling 6,080 MW, have been commissioned between FY 2007-08 and FY 2011-12. These include Adani, Mundra, Tata Mundra, Sipat, Jhajjhar, among others. 8For the 12th plan period, 24,000 MW of supercritical plants have been targeted for commissioning. 8One of the key areas of progress has been the extensive usage of gas insulated sub-stations of 400 kV and 765 kV levels, which has subsequently lead to reduced land requirement. 8As per the recent estimates, the land requirement is down 50%, from 120 acres to 60 acres for 765KV substation and 60 acres to 30 acres for 400KV substations. 8Moreover, large number of 765 KV D/C lines have been constructed to enable large capacity transmission on the same right of way (RoW). This has significantly reduced the land requirement from 128 metres to 69 metres. 8Besides this, the world's highest voltage line station of 1,200 kV transmission line, which was set up with indigenous technology, has been successfully tested. 8Further, the world's longest 800 kV HVDC multi-terminal bi-pole link is currently under implementation. The 2,000 km long link will connect Biswanath Chairali in north eastern region to Agra in western region.
ICPL invites bids for selecting EPC contractor for 1,320 MW project in Chhattisgarh-I: Scope of work
IFFCO Chhattisgarh Power Ltd. - a joint venture of IFFCO and Chhattisgarh State Power Holding Company Ltd (CSPHCL) - has invited bids under EPC basis for its proposed 2x660 MW super critical thermal power project in the state. 8The scope of work for the contractor shall include Engineering, Procurement and Construction (EPC) on a lump sum, turn key basis for the complete plant inclusive of the BTG and BOP packages for the two supercritical, pulverised coal-fired units. 8The contractor will be responsible for design, engineering, manufacturing, testing at the Manufacturing Works before despatch, supply, transportation to site, erection, commissioning, trial run and performance testing for the 1,320 MW plant. 8The first unit of 660 MW is expected to be commissioned within 44 months and second unit of 660 MW within 48 months from date of Notice to Proceed. (Click on our 'Tenders' section for more information) For reference purposes, the website details here the salient features of IPCL's proposed 1,320 MW plant at Village Salka in the Surajpur district of Chhattisgarh. 8The estimated capital expenditure for the proposed project is planned with a debt to equity ratio of 70:30. The debt would be financed by banks and financial institutions and the equity would be arranged by ICPL. 8The power generated at the power station will be shared between joint venture partners - CSPHCL and IFFCO - in 90:10 ratio. CSPHCL or its nominee will arrange distribution of its power within the State from the proposed EHV sub-station at Raipur. IFFCO shall wheel its share through the state CTU or STU grid to other states. 8Evacuation of Power from the proposed Power Station will be done at 400 kV level. Power from the plant switchyard will be evacuated through one double circuit line to the proposed 400 kV sub-station of CSEB located at Raipur. 8Coal will be used as the main fuel. Light Diesel Oil (LDO) and Heavy Furnace Oil (HFO) will be used for warm up and flame stabilization. Coal linkage from Tara Central Coal Block for the project has already been allotted by the Ministry of Coal. 8The Power Station will normally operate as base load plant. 8A flue gas desulphurisation (FGD) unit shall for the time being not deemed to be necessary for the proposed 2x660 MW project. However, the steam generator, flue gas path sections, induced draft fans and chimney shall be arranged such as to allow later easy installation of any FGD facility. 8Environmental Clearance for the project has been obtained from the Ministry of Environment and Forests.
ICCI urges govt to focus on energy projects in next budget
Islamabad Chamber of Commerce and Industry (ICCI) Saturday called for allocation of sufficient funds in the
China's PV installation could reach 6GW in 2012
China is expected to double its 2011 PV installation of 2.75GW in 2012 to around 5GW, according to market research firm, NPD Solarbuzz.
Nepal clears China's $1.6 B hydroelectric project amid irregularities
A parliamentary panel cleared the way for a Chinese company to build a $1.6 billion hydroelectric plant in Nepal.
China courting disaster with dam buildings: Report
A new report reveals that the more than 130 large dams being built in western China are in areas of high seismicity.
Emerson control system to be utilized at Indonesian coal-fired plant
A new 660MW supercritical power plant in Adipala, Indonesia will be installed with Emerson Process Management's Ovation expert control system.
India's off shore wind energy potential being explored
Studies reveal that wind power density in the Rameshwaram and Kanyakumari regions is in the range of 300-370 watt per square meter, and at a 50 meter hub height.
Studies in offshore wind energy in Tamil Nadu already underway
India's Centre for Wind Energy Technology is already in the process of exploring the off-shore wind potential in Tamil Nadu.
Japanese govt wants public to rely on nuclear power
Japan's government is rushing to restart two nuclear reactors by next month to convince the public that atomic energy is vital.
Indian power producers balk at Indonesia's coal tax plan
Indonesia's plan to impose a 25 percent export tax on coal may turn Indian power producers towards Australia and Africa.
Tata Power mulls conversion of gas-oil unit to coal firing
Tata Power has proposed to convert its 500 MW unit-6 of its Trombay combined cycle power plant from oil and gas firing to coal.
Indian nuclear power plant frightens Sri Lanka
An Indian nuclear power plant prompts Sri Lanka to take an unusual move.
Tamil Nadu eyes 4,300 MW capacity additon in FY13
Tamil Nadu is targeting to add 4,300 MW of generation capacity in financial year 2012-13, to address massive power shortage.
Hokkaido Electric shuts 175MW coal-fired unit after steam leak
Hokkaido Electric Power has suspended operations of the 175 megawatt coal-fired No.1 unit at its Naie plant after steam leaked from a boiler.
Japan uncertain on restarting nuke reactors
Japan wants more time to decide about restarting two offline nuclear reactors, according to the trade minister.
Commentary
Supply chain efficiency, skilled manpower are key for India’s renewable energy