JSW group tackles risks faced by its power projects

JSW Techno has revealed to investors the risks faced by its group company JSW Energy in the latter’s quest to become a major force in power generation.


The risks discussed include uncertainty about the merchant power segment in India, project financing, arranging fuel linkages, impact of spot prices on its two power plants, outcome of ongoing litigation and regulatory flux in general.

The private utility currently has four projects aggregating 8,420 MW of capacity under development and another 3,650 MW capacity which is either operational, or under construction.

"While it is in the process of arranging for financing of its projects from various banks and financial institutions, there is no assurance that it will be able to arrange financing on acceptable terms of at all. Other sources of financing may not be available and JSW Energy may not be able to obtain the capital necessary to fund its projects," says JSW.

JSW also contended that it may not be able to source additional coal from its fuel linkages or from other sources which will be required if its power projects are operated at higher PLFs. The company, which is also dependent on imported coal for fuel, will be impacted incase of any fluctuations in fuel prices or renegotiations.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Exclusives

Will the government pay for coal power exit in Vietnam?
The country’s coal power phase-out strategy sees renewables accounting for 67.7%–71.5% of the energy mix by 2050.
IPP
India removes licence requirement to build transmission lines for bulk consumers
The rule applies to those with at least 25 MW of load for inter-state connection and at least 10 MW for intra-state.
NEFIN Group works double time to catch up on projects
CEO Glenn Lim explains how a delay turned out good as the company aims to reach 667 MW of capacity by 2026.