NHPC laments even pre-construction activities take a decade

NHPC`s recent hydro project monitoring report revealed that preconstruction activities take more than a decade tocomplete.

The report  identified the usual culprits: the forest and environment clearances. Take the Teesta-IV for instance. After its ToR was approved by the environment ministry in 2009, stage-II forest clearance is expected to come through only by August, 2013. The likely date of getting environment clearance is September, 2012.

Yet, despite the nearly four year gap between ToR approval and forest clearance, it is more than probable that even this four year timeline will be overstepped.

The Indian government is already battling massive scams and such apathy to power projects.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you design and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Exclusives

Grid-forming inverters seize control to stabilise Asia’s power
Electricity demand is rising faster than the physical networks that deliver it.
Asia fusion market enters decisive phase with $5b China lead
The China Fusion Energy Corporation serves as a $2.1b national hub for artificial sun projects.
Grid links open fresh energy path for Singapore
Momentum builds around cross-border imports of solar, wind, and hydropower.