Rift with Pakistan ups Indian power project costs

The water disputes between India and Pakistan are making the costs of hydroelectric projects escalate, say India’s power department officials.

The cost of the 330MW Kishenganga project has gone up from approximately $490 million to $800 million, according to statistics provided by the power development department. The deadline for its completion has also been extended by two years.

Work started over Kishenganga river in Bandipore district of Jammu and Kashmir in October 2009 and was to be completed in five years.

Due to objections raised by Pakistan, which is protesting the diversion of river waters for the hydroelectric project citing provisions of the Indus Water Treaty, the project will get completed only by 2016, say power department officials.

Pakistan had raised objections over the 450 MW Baglihar power project in Ramban district of Kashmir. The project was to be completed in 2004, but it could be done only by 2008.

"Pakistan should have no objection as the project construction follows all norms of the Indus Water Treaty," a senior officer of the state government told IANS.

Jaringan listrik lemah Vietnam menghambat kebijakan pembelian listrik yang langsung

Infrastruktur energi yang buruk menghambat integrasi kapasitas baru dari proyek energi terbarukan (EBT).

Penutupan pembangkit listrik batu bara baru di ASEAN pada 2040 mungkin tercapai

Penambahan pembangkit batu bara baru dan retrofit pembangkit yang ada menjadi risiko lebih besar dalam transisi.

ADB menyetujui pinjaman senilai $500 juta untuk mendukung transisi energi Indonesia

Ini bertujuan membangun kerangka kebijakan yang kokoh dalam mendukung peralihan menuju energi bersih.

Avaada meningkatkan beban energi terbarukan untuk penuhi permintaan pusat data India

Perusahaan menargetkan kapasitas energi terbarukan sebesar 30 gigawatt pada 2030.

Asia-Pasifik mungkin tidak mencapai target energi terbarukan

Negara-negara di kawasan itu harus menarik investasi untuk memajukan tujuan energi bersih mereka.

Laba bersih Adaro turun 12% menjadi $880 juta di Semester 1

Pendapatan turun 15% menjadi $2,97 miliar pada periode tersebut.

ACEN dan Barito Renewables bermitra untuk mempercepat energi angin di Indonesia

Kemitraan ini akan dijalankan oleh anak perusahaan mereka.

Malaysia diminta mengintegrasikan jaringan listrik untuk mempercepat pertumbuhan tenaga surya

Pembatasan penetrasi tenaga surya ke jaringan pada 24% dari permintaan puncak dapat menghambat ekspansi.