Ørsted energises first offshore export cable for Greater Changhua 2b and 4

This is an important step towards generating the first power.

Ørsted has completed the installation and energised the first offshore export cable system for the 920 megawatt Greater Changhua 2b and 4 offshore wind farms.

The company said this is the first of three export cable systems connecting CHW2204 to Taiwan's grid.

This achievement involved the mobilisation of 16 vessels and 45 specialised personnel.

With this development, the company said it inches closer towards the projects’ final phase, the generation of first power.

Follow the link for more news on

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you design and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Top News

Grant funds acceleration of ASEAN Power Grid development
The funding will help finance the conduct of studies and establishment of new regulatory.
AMPIN Energy secures $50m FMO investment for Indian renewables
The $50m FMO investment provides long-term capital for AMPIN’s renewable expansion.
Project
Do coal breakdowns threaten Australia's energy reliability and prices?
Replacing unreliable coal with renewables and storage protects households from price volatility.