, Vietnam
Photo via EVN

Ialy Hydropower Expansion Unit 2 goes online

It was 18 days ahead of schedule.

Vietnam Electricity (EVN) has announced that unit two of the Ialy Hydropower Plant Expansion work has been energised and synchronised on 13 December.

Construction at the Ialy Hydropower Plant Expansion Project started mid-2021. It has two units and a designed capacity of 360 megawatts, and was assigned by EVN to the Power Project Management Board 2 (EVNPMB2) as the investor representative. Power Engineering Consulting Joint Stock Company 1 is the consulting unit for the project design in each phase.

EVN said the project has implemented innovative construction solutions. Notably, a key strategy involved the simultaneous rotor assembly for Units 1 and 2, enabling parallel site deployment and a demanding 24/7, 3-shift operation schedule, including weekends and holidays.

This approach was crucial for commencing power generation for Unit 2 immediately following Unit 1's activation, achieving an 18-day lead over the anticipated schedule and significantly reducing the overall project timeline by approximately 3 months.

Upon commissioning, this project will augment Vietnam's power system's capacity, particularly during peak demand periods. This enhancement will optimise system-wide operational efficiency, maximise the utilisation of the water resource, and boost annual power generation by approximately 233 million kilowatt-hours.

This project also contributes to mitigating carbon emissions by reducing the operational intensity and runtime of existing units.

Jaringan listrik lemah Vietnam menghambat kebijakan pembelian listrik yang langsung

Infrastruktur energi yang buruk menghambat integrasi kapasitas baru dari proyek energi terbarukan (EBT).

Penutupan pembangkit listrik batu bara baru di ASEAN pada 2040 mungkin tercapai

Penambahan pembangkit batu bara baru dan retrofit pembangkit yang ada menjadi risiko lebih besar dalam transisi.

ADB menyetujui pinjaman senilai $500 juta untuk mendukung transisi energi Indonesia

Ini bertujuan membangun kerangka kebijakan yang kokoh dalam mendukung peralihan menuju energi bersih.

Avaada meningkatkan beban energi terbarukan untuk penuhi permintaan pusat data India

Perusahaan menargetkan kapasitas energi terbarukan sebesar 30 gigawatt pada 2030.

Asia-Pasifik mungkin tidak mencapai target energi terbarukan

Negara-negara di kawasan itu harus menarik investasi untuk memajukan tujuan energi bersih mereka.

Laba bersih Adaro turun 12% menjadi $880 juta di Semester 1

Pendapatan turun 15% menjadi $2,97 miliar pada periode tersebut.

ACEN dan Barito Renewables bermitra untuk mempercepat energi angin di Indonesia

Kemitraan ini akan dijalankan oleh anak perusahaan mereka.

Malaysia diminta mengintegrasikan jaringan listrik untuk mempercepat pertumbuhan tenaga surya

Pembatasan penetrasi tenaga surya ke jaringan pada 24% dari permintaan puncak dapat menghambat ekspansi.