Lack of manpower, transport option stymie BHEL

 

The timely provision of equipment to the project sites is hampering BHEL's on time commissioning of power projects.

 

Bharat Heavy Electrical has long been the target of censure from various quarters with respect to its frequent inability to fulfill its supply commitments.

Currently, the developer has to strengthen all connecting bridges, which eats up a lot of time.

There are need for clearances from the National Highway Authority of India for consignments requiring use of National Highways. Unlike Railways, NHAI has not agreed to a "Single Window` concept. Procedural delays due to the above leads to considerable wastage of time.

On the other hand, for items required to be imported from abroad, a no objection certificate is required from TRANSCHART, for hiring vessels other than from Shipping Corporation of India Limited.

Follow the link for more news on

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you design and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Top News

Utility scale battery storage costs fall to US$125 per kWh
Core equipment costs can rise to around US$100 per kilowatt-hour or more in markets with higher tariffs, among others.
NTPC boosts solar capacity at Khavda projects in Gujarat
The solar energy expansion strengthens India’s renewable footprint nationwide.
Power Utility