, India

Full load at unit 2 of Bellary thermal project to be delayed

Delays at the turbine generator box up works at the unit-2 of Bellary stage 2 thermal power project will likely push back the full load achievement by another 4 months.

 

The project, being executed  by the Karnataka Power Transmission Corporation Limited was initially envisaged to achieve full load generation in August 2011.

While the Turbine generator has been erected, non completion of box up works have held up the project, even as TG on barring gear is likely to be complete by the end of next month.

Further, oil synchronization works are also likely to be completed by this month, a delay of roughly 15 months over that initially envisaged by the power utility.


The Bellary Thermal Power Stationis located at Kudatini, Bellary District of Karnataka and is a venture is a venture of Karnataka Power Corporation Limited (KPCL). The power station will be developed in two stages of 500 MW each.
 

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!