Bangladesh facilitates logistics to Indian Power Plant

Bangladesh will allow transport of equipment in its territory for a power plant in India's north eastern state of Tripura.




According to the Daily Star,  a total of 96 Over-Dimensional Cargoes will be carried through Bangladesh for the 726MW Palatana power project.

Under the MOA signed between Bangladesh and India, cargo will start from West Bengal's Raimongal and enter Bangladesh at Angtihara and go up to Ashuganj river port by inland waterways.


India will not pay any fees or service charges for this transit; however, it will provide Bangladesh $3.6 million for the development of Ashuganj river port terminal and 49 kilometr of roads.


The MOU is the first such multi-modal transit accord signed by Bangladesh allowing access by land since 1965.


 

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Top News

Renewable energy share in world’s electricity mix surpasses 30%
China is the main contributor as it comprises over half of the wind and solar installations.
Power Utility
ACEN’s net income surges 34% YoY in Q1
The company has reached its 2025 5 GW renewables capacity target during the period.
IPP

Exclusives

Will the government pay for coal power exit in Vietnam?
The country’s coal power phase-out strategy sees renewables accounting for 67.7%–71.5% of the energy mix by 2050.
IPP
India removes licence requirement to build transmission lines for bulk consumers
The rule applies to those with at least 25 MW of load for inter-state connection and at least 10 MW for intra-state.